Construction Plan I-2025-011

Plan # I-2025-011
Plan Type I - Paving Improvements Plans
Film Roll
Location
Description

Road Recovery Proposition 101 Package 5, 5th Street: Alvernon Way to Wilmot Road - includes pavement reconstruction, new curb access ramps, driveways, curb, asphalt and AB, and fully rebuilding of 5th Street from Chantilly Drive to Sahuara Avenue for it to drain and with Concrete, and reconfiguration from 4-lane roadway to 2-lane roadway with new striping - (Kimley>Horn)
NOTE: this was originally from Country Club Rd to Wilmot but the portion from Country Club Rd to Alvernon Way was added to 5th & 6th Street Pedestrian Walkability Project I-2024-019